Goodyear Wolverhampton – Bulk Earthworks, Remediation and Site Preparation

Following the successful delivery of the demolition phase of the project, EDR were appointed to carry out an extensive package to prepare the site for construction of several hundred new homes. The project comprised of removal of all sub-structures on site, proof digging, ground remediation, a 100,000m3 cut/fill exercise with a comprehensive compaction specification. The […]

Dark House Lane, Coseley – Bulk Earthworks, Remediation and Site Preparation

This project involved asbestos removal and demolition of large foundry buildings as well as an extensive remediation and reprofiling 55,000m3 of material used as a tip site. The remediation works included asbestos in the ground, various hot-spots and Japanese Knotweed present. The excavated material required an extensive program of sorting and screening before the materials […]

Wilstead Industrial Estate, Bedford – Earthworks

Following the successful demolition phase, the EDR Earthworks Division were contracted to carry out a cut and fill exercise on the site. This was followed by the installation of extensive piling mats for two new large industrial units that were to be constructed by our client. Despite various additional works being required, the project was […]