Fire Training Centre, Smethwick

EDR were appointed to carry out a phased demolition and site clearance to the former Fire Training Centre in Smethwick, West Midlands.

The initial phase included the demolition of the de-construction of a steel training tower and the smoke-house training facility.

The second phase involved the removal of licensed and non-licensed asbestos containing materials. The extensive structures were demolished with slabs, foundations and basements removed. All of the arisings were crushed for our client to re-use in their future development and lessening the environmental impact of the project.

The works were completed whilst working around live services including careful separation from a live sub-station and a gas main.

The project was completed on program and within the original budget for a happy client.